February 2012
- Pool Area and Pool Deck is 95% completed Siena Park Residences
- Clubhouse is 100% complete Siena Park Residences
- Auburn Building is 100% complete Siena Park Residences
- Citrine Building is 95% completed Siena Park Residences
- Lilac Building is 60% completed Siena Park Residences
- Magenta building is 70% completed Siena Park Residences
- Structural works of Indigo building is now at 2nd level Siena Park Residences
- Structural works of Cerise Building is now at 2nd level Siena Park Residences
- Structural works of Olive Building is now at lower ground Siena Park Residences
- Structural works of Crimson Building is now at lower ground level Siena Park Residences
- Structural works of Plum Building is now at lower ground Siena Park Residences